Your web browser is out of date. Update your browser for more security, speed and the best experience on this site.

Update your browser
DPR Logo
Exterior view of data center under construction

CoreSite LA3 Data Center

CoreSite LA3 Data Center | Los Angeles, CA

DPR Pushing Forward Towards Fall 2020 Completion of Major New Data Center for CoreSite in Downtown Los Angeles

Despite significant permitting and utility-related design changes, weather impacts and the unique challenges of delivering a major project in the midst of COVID-19, DPR is on track to complete one of its largest ever data center projects in Southern California on schedule in 2020.

Project Details

The CoreSite LA3 data center project in downtown Los Angeles includes core and shell construction of an approximately 180,000-sq.- ft., four-story data center facility and a full floor build-out that will distribute six megawatts of critical IT power. Planned future phases will result in a total 18 megawatts of IT capacity.

The new data center is located adjacent to the historical USPS Terminal Annex building and active rail lines from nearby Los Angeles Union Station. Originally planned to include an adjacent four-story parking structure, the project underwent a major design revision during preconstruction when coordination with the local utility revealed the need for an onsite utility substation, replacing the parking structure.

The Challenges

Extensive and ongoing coordination with the local power company has been a key challenge in the planning and construction of this project. Early on the team was challenged to reroute the existing power feed to the existing building to allow construction to begin on the new facility and substation, which will then tie back into the new building. They also needed to incorporate a major design revision that required the substation to be constructed onsite in lieu of a planned parking structure. The team spent several months working through parking solutions and variances, delaying construction start by several months.

Planning and permitting challenges were factors when the building’s design was questioned about how it would blend in with neighboring structures. Modification to the exterior skin design was required, and the team brought on board a local architect that had been involved in other projects in the vicinity.

Finally, greater than average rain delays and the unexpected and unique impacts of managing a largescale project in downtown LA during the onset of COVID-19 have added additional layers of complexity to this job.

Equipment in the basement of CoreSite Datacenter.
A crane lifts materials to the roof of the building for construction.
aerial view of the construction site with surrounding buildings
The Solutions

Success on the CoreSite project has required a team that is adaptable, flexible and experienced in working through the complex challenges associated with building a major data center facility in a busy urban environment.

DPR differentiated itself during project selection by showcasing its prefabrication capabilities, hosting the owner on a factory tour of Digital Building Components. DBC ultimately prefabricated the structure’s entire exterior wall paneling system offsite, resulting in quality control and schedule advantages.

DPR self-performed approximately 10% of the subcontract value, using SPW concrete and drywall crews.

Additionally, the project team demonstrated its strength adapting to the worksite challenges of COVID-19, showing an overriding focus on safety as a top priority. When the crisis hit, they switched to double shift work to accommodate social distancing issues, instituted daily worker temperature checks and hired a third-party cleaning company to continuously clean the jobsite daily, among other measures. The project has been recognized in the LA region as a leading example of a project that takes a proactive approach to worker safety while maintaining operations during COVID-19.

CoreSite LA's exterior wall construction.
Drying concrete after being laid by crews.
Crews work at night building exterior steel structure