data center interior

CHRISTUS Healthcare Data Center

CHRISTUS Healthcare Data Center | San Antonio, Texas

This Tier 3, 47,000-sq.-ft. data center includes 15,000 sq. ft. of data center white space, 20,000 sq. ft. of office space and 12,000 sq. ft. of electrical support space. The facility includes a Security Operations Center (SOC) and a Network Operations Center (NOC).

The owner's initial plan called for two distinct phases: shell construction and data center finishout, with demobilization from the site between the two. This was to accommodate the company's fiscal year and funding availability. DPR recommended compressing the shell construction by two months and starting later, eliminating the need for additional demobilization/mobilization and saving on the overall budget.

Partners

Project Scope

Completion of the building slab was a critical schedule milestone, as it was to serve as the casting bed for the tilt-up panels. However, the electrical underground design would not be ready in time for the accelerated schedule. Under the original schedule, the massive amount of electrical conduit needed would have been installed below the slab prior to it being poured. To allow construction to proceed while electrical design was in progress, the project's structural engineers analyzed the foundation grade beam structure and made recommendations for proceeding with the slab. The approach was to utilize the four feet of flowable, lightweight concrete under the exterior grade beams for access. When the building construction was complete, a portion of the interior slab was removed and sections of the lightweight concrete excavated. Electricians were then able to run conduit from the interior of the building to the exterior yard while the interior build-out progressed.

The city utility also did not have sufficient infrastructure to support the facility by the accelerated completion date. They agreed to have power ready in time for the original completion date but could not guarantee service for the compressed construction schedule. The team enlisted a temporary services design and implementation company to design and provide temporary cooling and dehumidification of the interior to allow sensitive activities to continue without hindering the schedule.

We think you'll like this, too.