The new Gunnison County Courthouse retains elements of the original 1881 courthouse while providing additional space for the courtroom, staff offices and meeting rooms.

Partners

  • Client Gunnison County

The Big Picture

After completing the demolition and hazardous material abatement of the dilapidated 1881 courthouse, GE Johnson constructed this new facility – a sturdy steel structure with veneer masonry, metal wall panels, and a curtain wall. The new courthouse provides appropriate security with three new courtrooms, administration space, and other public use areas. Sustainable strategies such as a large geothermal system and passive ventilation were also implemented.

Timber trusses were salvaged and structurally upgraded from the original building and 620 sq. ft. of the ceiling was refurbished and reused in the main entry of the new courthouse. An accent wall was decorated with 800 sq. ft. of brick salvaged from the 1881 structure.

46,000

Total Square Feet

40

The number of 300-foot-deep wells comprising the new geothermal heating system.

134

Years Old. Age of the bricks and lumber used from the original courthouse.

Ingenuity in Action

In an effort to complete this remote project on schedule and also support the local economy, GE Johnson enlisted subcontractors from the Gunnison area to perform demolition, earthwork, concrete, rough carpentry, damproofing, metal roofing and siding, EPDM roofing, door installation, wood windows, decorative ceilings, tile, marble flooring, carpet, signage, fire protection and utilities.

Exterior courthouse rendering with original courthouse photo overlay
Interior courthouse with rows of chairs and benches
Exterior courthouse with interior lights on and large trees in front
Interior wall with curved windows
Exterior courthouse rendering with original courthouse photo overlay
Interior courthouse with rows of chairs and benches
Exterior courthouse with interior lights on and large trees in front
Interior wall with curved windows

Fast Facts

  • The project was delayed with the south wall of the 1881 building collapsed and the area had to be redesigned. Despite this and other setbacks, the project was completed within three days of schedule and on budget.