Stories

Advancing a Paradigm Shift in Construction at LCI Congress

DPR's Mike Cummings and Banner Health's Aaron Zeligman discuss what will be most important for the end users of the project.
DPR's Mike Cummings and Banner Health's Aaron Zeligman discuss what will be most important for the end users of the project. Courtesy of Mindy Gray

How can contractors and their partners collaborate with customers to deliver projects more efficiently? Or change the way all stakeholders approach projects to drive success? Those topics are the core of what DPR and its partners will discuss in six presentations at the 20th annual LCI Congress, the flagship event of the Lean Construction Institute (LCI), Oct. 15-19 in Orlando, Florida.

The paradigm shift is being advanced through a focus on jobsite culture, better alignment with customer expectations and leveraging technology in new ways. By breaking free of traditional workflows, new efficiencies can be realized leading to benefits for all project stakeholders.

Three of DPR's six presentations are discussed below. To learn more, click on the section headlines and view videos detailing the topics.

Matching Methods with Culture

When it comes to safety, we know procedures and protocols won’t prevent incidents unless a strong jobsite culture of caring and risk rejection exists. Similarly, all the tools of Lean, from kaizen to pull planning, will be limited in their effectiveness without the right culture. True commitment to continuous improvement, for instance, requires trust in your teammates and a sense of a shared goal that’s bigger than one’s self.

DPR’s Daniel Berger understood that his customer at HCA Northwest Hospital Medical Center in Margate, Florida wanted the project team to share its Lean goals. He knew, though, that simply executing Lean methods would only take the team so far.

“For the last 10 years, there’s been such a focus when it comes to Lean construction on things like ‘what can we prefab?’ and ‘what can we do more efficiently,’” Berger said. “We’ve lost track of the soft skills and what those can accomplish on the job and how those skills can help build a culture that supports the Lean process.”

At LCI Congress, Berger and DPR’s customer, HCA, will discuss how they worked together to achieve results. The key was creating a team that hold one another accountable and can thrive during the “tough” conversations that take place during any project. They will also discuss how planning took a whole-project approach rather than being individual scope-specific, how productivity and safety performance improved vs. baselines, and how, once the project is completed in 2019, the culture will continue on future projects.

Aligning Lean Approaches with Customers

When DPR’s team in Phoenix completed the first phase of a large hospital project for Banner Health, it achieved zero defects. Why fix what’s not broken for the second phase? The customer shifted its approach to quality by focusing on Distinguishing Features of Work (DFOW) that were closely associated with the end use of the building and patient care, building a Lean program to support them.

“When people think of quality, they think of aesthetics,” said DPR’s Mike Cummings, who is presenting at LCI Congress. “For Banner, it’s the functionality of those things and how they come together and how they will eventually affect their patients.”

As a result, the entire project team shifted its approach to focus on DFOW and saw fantastic results. For example, work on elevator lobbies (a DFOW) included eight RFIs prior to work starting and zero once work was under way. Trade partners saw increased productivity, too. The team originally planned for 53 days of elevator lobby work, but by aligning around DFOW resulted in only 32 days of work—all with zero defects. Similar improvements were achieved across the project because of increased communication and focus on what was important for all stakeholders.

Technology as a Time Machine

The Lean method of a gemba walk involves going out in the field to see the work and collaborating with partners to address a specific issue in production or key performance indicator. But what if the work doesn't exist yet and won’t be for another year? Easy: use a time machine.

“With 4-D, we can now collaborate more efficiently with our partners to deliver predictable results,” said DPR’s Charlie Dunn. “You can deliver much faster, so you can get a drug to market sooner or a hospital to treat patients earlier.”

Essentially, technology has unlocked the ability for partners to virtually walk through a job site far in advance of the work being put into place. Teams can gain a common understanding of the challenges of a dynamic construction environment, viewing it differently than the fixed nature of an assembly line. As a result, stakeholders can test strategies and make mistakes early—and virtually—while avoiding expensive problems that traditionally emerge after crews have mobilized.

At the 2018 LCI Congress, DPR and its partners will show how this is working to improve delivery of a large project in Orlando. Using 4-D eliminates waste throughout the delivery process and illustrates how we’re utilizing innovative technology with exciting visualizations that promise to alter the way we construct in the future.