<?xml version="1.0" encoding="utf-8"?>
<rss version="2.0"
    xmlns:dc="http://purl.org/dc/elements/1.1/"
    xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
    xmlns:admin="http://webns.net/mvcb/"
    xmlns:rdf="http://www.w3.org/1999/02/22-rdf-syntax-ns#"
    xmlns:atom="http://www.w3.org/2005/Atom"
    xmlns:content="http://purl.org/rss/1.0/modules/content/">
    <channel>
    
  
    <title>DPR Safety Projects</title>
    <link>http://www.dpr.com/projects/</link>
    <description>Projects from the DPR website posted in "Safety"</description>
    <dc:language>{channel_language}</dc:language>
    <dc:creator>website@dpr.com</dc:creator>
    <dc:rights>Copyright 2011</dc:rights>
    <dc:date>2011-12-19T18:08:10+00:00</dc:date>
    <atom:link href="http://www.dpr.com/rss/projects/expertise/safety" rel="self" type="application/rss+xml" />
    <admin:generatorAgent rdf:resource="http://www.expressionengine.com/" />

  
  <item>
    <title>Hines Riverfront Plaza Cooling Tower Replacement</title>
    <link>http://www.dpr.com/projects/hines-riverfront-plaza-cooling-tower-replacement</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/hines-riverfront-plaza-cooling-tower-replacement#when:16:09</guid>
    
    <content:encoded><![CDATA[<p>
	After successfully completing a tenant fit-out and renovation in the Riverfront Plaza, DPR was selected to replace the existing cooling towers on the facility&#39;s East and West towers.</p>
<p>
	Specifically, this project included:</p>
<ul>
	<li>
		Replacing two (2) existing 2000 ton / 4800 gpm cooling towers (built in 1992) with new units - one cooling tower on the roof of each building</li>
	<li>
		Installing new Variable Frequency Drives</li>
	<li>
		Supporting electrical and software upgrades to the existing BAS system</li>
</ul>
<p>
	The project team carefully coordinated the construction plan, as both 20-story buildings remained occupied and operational, and were located in a tight urban location.&nbsp;</p>
<p>
	In order to minimze disruptions, the project was split into two weekends - one tower per weekend, each with a 56-hour shutdown window. The existing cooling towers were drained, demo&#39;d and removed, with new cooling towers subsequently lifted and assembled using a 550-ton crane.&nbsp;</p>
<p>
	DPR utilized lean manufacturing techniques in order to accomplish this large amount of work within such a short time frame.&nbsp;</p>
<p>
	Lean techniques included:</p>
<ul>
	<li>
		Reassembling the the cooling towers at the mechanical subcontractor&#39;s local facility</li>
	<li>
		Fabricating and fitting-up the supply and return piping with control valves before scheduled shutdown</li>
	<li>
		Disassembling the cooling towers along with the prefabricated piping</li>
	<li>
		Shipping cooling towers to the jobsite for just-in-time lifting to the roof</li>
</ul>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 23 Jan 2013 16:09 GMT</pubDate>
  </item>
  
  <item>
    <title>University of Virginia Old Jordan Hall Renovation</title>
    <link>http://www.dpr.com/projects/university-of-virginia-old-jordan-hall-renovation</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/university-of-virginia-old-jordan-hall-renovation#when:20:34</guid>
    
    <content:encoded><![CDATA[<p>
	Spanning two and a half years, the UVA Old Jordan Hall Renovation involved the complete overhaul and replacement of the 40-year-old mechanical and electrical systems while the seven-story medical research facility remained occupied and operational.</p>
<p>
	A few of the major project components included:</p>
<ul>
	<li>
		11 new Air Handling Units (AHUs) delivering 300,000 CFM Supply Air through a new SA distribution infrastructure</li>
	<li>
		New Steam System that delivers 60,000 pounds/hr steam through a new distribution system</li>
	<li>
		10 new Lab Exhaust Fans that provide 370,000 CFM of exhaust, along with an Energy Recovery System</li>
	<li>
		New 2,000 KW Emergency Generator and new Emergency Electrical Distribution System</li>
	<li>
		New 430 GPM Reheat System including all pumps, heat exchanges, and distribution</li>
</ul>
<p>
	All of the new equipment tied in to the University&#39;s campus-wide systems control infrastructure which allowed remote monitoring and control of all new systems. DPR worked with the team during preconstruction to devise temporary connections and bypasses in order to provide seamless environmental conditions to stakeholders.</p>
<p>
	The DPR team utilized 3D and 4D BIM to plan project phasing and perform conflict analysis. BIM enabled the identification and resolution of five major conflicts before construction began. The team also devised a plan for structural improvements that did not impact research operations by performing the work from the shaft side of the beams and columns. This work led to the discovery of unknown asbestos fireproofing in the columns and lead paint that had to be mitigated. By utilizing BIM, the project team was able to complete the project under budget and ahead of schedule.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 02 Jan 2013 20:34 GMT</pubDate>
  </item>
  
  <item>
    <title>Savannah State University, Student Housing</title>
    <link>http://www.dpr.com/projects/savannah-state-university-student-housing</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/savannah-state-university-student-housing#when:19:37</guid>
    
    <content:encoded><![CDATA[<p>
	Phase 1 of the design-build project included the renovation of 22,446 SF Camilla Hubert Hall (78 beds) and the construction of two new residence halls, 28,858 SF Tiger Pointe (106 beds) and 43,941 SF Tiger Place (173 beds). Each of the buildings offers one- and two-bedroom units.&nbsp; Phase 2 includes Tiger Court, a 81,928 SF new residence hall with 325 beds and the renovation of two existing historical buildings, Morgan and Adams Halls, totaling 13,170 SF. All of the buildings were renovated and constructed to comply with historical guidelines.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sat, 01 Dec 2012 19:37 GMT</pubDate>
  </item>
  
  <item>
    <title>Novelis R&amp;D Laboratory</title>
    <link>http://www.dpr.com/projects/novelis-rd-laboratory</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/novelis-rd-laboratory#when:15:09</guid>
    
    <content:encoded><![CDATA[<p>
	The project is in an existing 162,000-sq.-ft., single-story warehouse and office building in an LI zone. This building consolidated two existing facilities currently located out of state and houses research and development, laboratory, microscopy, offices and support spaces focused on the metal casting and fabrication business. The facility included (2) Air Cooled chillers, Pre-action and Clean Agent Fire Protection system. Specialized requirements include a warehouse housing manufacturing and testing equipment.</p>
<p>
	The scope included a total of (17) new fume hoods, oxygen and nitrogen piping at the lab benches and some of the labs are ISO 17025 certified. Much of the equipment, including a pilot beverage can production line, was relocated from existing remote facilities located out of state. This required many trips and careful coordination of highly specialized equipment and unique utility requirements that are duplicated in the new facility. The equipment required substantial MEP infrastructure. A majority of the equipment required substantial MEP infrastructure and significant base building modifications such as structural enhancement for overhead equipment, mechanical systems and roof top equipment.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 12 Sep 2012 15:09 GMT</pubDate>
  </item>
  
  <item>
    <title>HCA Nashville Data Center</title>
    <link>http://www.dpr.com/projects/hca-nashville-data-center</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/hca-nashville-data-center#when:00:32</guid>
    
    <content:encoded><![CDATA[<p>
	Currently under construction outside of Nashville, TN, HCA&rsquo;s new data center is an expandable facility, capable of meeting the healthcare provider&rsquo;s immediate needs and accommodating future growth. The initial phase is the construction of a 100,000-sq.-ft. structure with a 30,000-sq.-ft. raised floor with 12 MW systems and related utilities, 10,000-sq.-ft. office area, and warm shell space for future expansion.</p>
<p>
	DPR&rsquo;s design-build partner on the project is PageSoutherlandPage. Together they have completed approximately $200 million in data centers in Texas.</p>
<p>
	<strong>Technical Details</strong>: The data center will be outfitted with 12 MW systems over 30,000 sq. ft. of white space with the following equipment set:</p>
<ul>
	<li>
		1 N Utility Feed At 161 KV (By Others)</li>
	<li>
		Single-Ended 161 KV Substation Rated At 20 MVA With Provisions For Double Ending (By Others)</li>
	<li>
		Tri-Bus 15 KV Switchgear With Auto Transfer Capability</li>
	<li>
		Underground Medium Voltage Distribution In Tri-Bus Configuration For Critical Power</li>
	<li>
		Overhead Low Voltage Distribution To White Space</li>
	<li>
		Underground Medium And Low Voltage Distribution In Traditional A/B Bus Configuration For House Power And Mechanical Loads.</li>
	<li>
		3 Mode (Single Bus, Double Bus, And Tri-Bus) Medium Voltage N+1 Diesel Rotary UPS (DRUPS) Plant With 24 Hour Fuel Storage</li>
	<li>
		120/ 208V Remote Distribution Panels (RDP&rsquo;s) And Remote Power Panels (RPP&rsquo;s) For White Space Legacy Equipment</li>
</ul>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Tue, 19 Jun 2012 00:32 GMT</pubDate>
  </item>
  
  <item>
    <title>PNC Plaza</title>
    <link>http://www.dpr.com/projects/pnc-plaza</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/pnc-plaza#when:17:45</guid>
    
    <content:encoded><![CDATA[<p>
	PNC Plaza, a 757,000-sq.-ft., 33-story tower, was a marquee project for the community as it was the first true high-rise, mixed use project in downtown Raleigh, NC. The tower includes a 1-story lobby with retail and service core, 11 stories of office space, a 1-story transfer floor, 11 stories of condominium space, and an 8-level parking deck.</p>
<p>
	The hardscape ties in with the downtown scheme, and the sky-line is improved by incorporating existing textures and materials with a more modern look, transitioning in the old with the new.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 08 Apr 2012 17:45 GMT</pubDate>
  </item>
  
  <item>
    <title>Kennesaw State University, South Campus Village</title>
    <link>http://www.dpr.com/projects/kennesaw-state-university-south-campus-village</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/kennesaw-state-university-south-campus-village#when:19:46</guid>
    
    <content:encoded><![CDATA[<p>
	The South Campus Village includes 200,647 SF of 4 and 5-story wood framed student housing buildings&nbsp; with&nbsp; 451 beds.&nbsp; Buildings include open breezeway corridors and brick and hardiplank siding exteriors.&nbsp; Each unit includes a full kitchen, laundry and each bedroom has a private full bath.</p>
<p>
	The project includes seven acres of earthwork, hardscape and landscape including a 900,000-gallon underground storm water detention vault. The project also includes an outdoor amphitheatre.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 19:46 GMT</pubDate>
  </item>
  
  <item>
    <title>Georgia State University, University Commons</title>
    <link>http://www.dpr.com/projects/georgia-state-university-university-commons</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/georgia-state-university-university-commons#when:19:45</guid>
    
    <content:encoded><![CDATA[<p>
	University Commons is a student housing complex located on a 4.2 acre site at Georgia State University in downtown Atlanta. The development consists of 4 buildings ranging from 8 to 14 stories, with 2,000 beds, 17,982 SF of retail space and 786 parking spaces. The buildings circle a large landscaped courtyard and provide students with an environment for living and learning. The buildings have an urban look compatible with the architectural character of the main campus and downtown Atlanta.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 19:45 GMT</pubDate>
  </item>
  
  <item>
    <title>Georgia Northwestern Technical College, Gordon Campus Phase III Classroom Building</title>
    <link>http://www.dpr.com/projects/georgia-northwestern-technical-college-gordon-campus-phase-iii-classroom-bu</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/georgia-northwestern-technical-college-gordon-campus-phase-iii-classroom-bu#when:19:31</guid>
    
    <content:encoded><![CDATA[<p>
	The Georgia Northwestern Technical College - Gordon Campus - Phase III Classroom Building includes a 48,000 SF classroom and conference center. The new facility includes faculty offices, classrooms, a 500-seat conference room, laboratories that complement the college&rsquo;s cosmetology, dental, nursing, computer and education programs, as well as a media center, bookstore and catering kitchen. The constraints of working on an active campus required the project to be phased, with a new parking lot and new entry drive.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 19:31 GMT</pubDate>
  </item>
  
  <item>
    <title>Armstrong Atlantic State University Phase III Windward Commons</title>
    <link>http://www.dpr.com/projects/armstrong-atlantic-state-university-phase-iii-windward-commons</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/armstrong-atlantic-state-university-phase-iii-windward-commons#when:19:28</guid>
    
    <content:encoded><![CDATA[<p>
	This $20 million, 176,543 SF, two 4-story wing residence hall is the home for 569 students on the Armstrong Atlantic University campus. The unit plans are a common two private bedroom/one bath suite with a unique two person semiprivate suite arrangement. Interior amenities include a central lobby, game room that doubles as a media room with black-out shades and a computer modeled high-tech audio/video system, two smart classrooms, amenity area, and a central laundry room. Each floor also contains study areas and community TV rooms.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 19:28 GMT</pubDate>
  </item>
  
  <item>
    <title>Galleria Manor of Smyrna</title>
    <link>http://www.dpr.com/projects/galleria-manor-of-smyrna</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/galleria-manor-of-smyrna#when:18:28</guid>
    
    <content:encoded><![CDATA[<p>
	Galleria Manor, built by the joint venture of Hardin Construction and Chap Ashmore &amp; Associates, is a 113,523 sq. ft., four-story senior apartment community housing 88-units. The project achieved LEED&reg; Gold Certification. All units are ADA accessible and 5% of the units are fully equipped for persons with disabilities including units for the hearing and vision impaired. Unique features include handicap adaptable units, nurse call systems, multiple elevators, and pull cords in bedrooms and bathrooms that activate a light outside the unit. The building features community areas including a library, multipurpose space for meetings and classes, a fitness center and a computer work area.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 18:28 GMT</pubDate>
  </item>
  
  <item>
    <title>WellStar Kennestone Hospital Bed Tower</title>
    <link>http://www.dpr.com/projects/wellstar-kennestone-hospital-bed-tower</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/wellstar-kennestone-hospital-bed-tower#when:18:12</guid>
    
    <content:encoded><![CDATA[<p>
	The seven-story, 80-bed tower addition, built by the joint venture of RodgersHardin, was constructed on top of a loading dock. Due to tight site, material delivery and staging were crucial to ensure minimal disturbance and uninterrupted services. Ongoing infection control was vital due to the close proximity and tie-ins with the existing facility.&nbsp; Mechanical systems were needed to facilitate the new Bed Tower and a central energy plant expansion was incorporated. Healthcare elements included a 12 bed CV-ICU, Nuclear medicine suite, two 64-slice CT rooms, and the first Cyberknife procedure suite in the state.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 18:12 GMT</pubDate>
  </item>
  
  <item>
    <title>Terminus 100</title>
    <link>http://www.dpr.com/projects/terminus-100</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/terminus-100#when:17:40</guid>
    
    <content:encoded><![CDATA[<p>
	Terminus 100 is a 27-story, 582,000-sq.-ft. office tower with approximately 69,500 sq. ft. of ground-level retail and a 14-story, 2,100-car parking structure. The building includes a health spa, fine dining, boutique retail and other upscale amenities. Terminus 100 is part of a 4-million-sq.-ft. urban mixed-use development in the Buckhead district of Atlanta.&nbsp;</p>
<p>
	Terminus marked a new direction in development for this city, which has a rapidly growing business district but remains largely a commuter town. The dense development is rendered airy and accessible with predominantly clear glass cladding, multiple entryways, interior streets and courtyards and a pedestrian level that is devoted to store fronts and restaurants.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 17:40 GMT</pubDate>
  </item>
  
  <item>
    <title>3344 Peachtree</title>
    <link>http://www.dpr.com/projects/3344-peachtree</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/3344-peachtree#when:17:10</guid>
    
    <content:encoded><![CDATA[<p>
	3344 Peachtree is a 50-story tower which includes 469,921 sq. ft. of Class A office and retail space, 82 condominium units, and an 11-story, 1,631-space parking structure. The building is conveniently located in the Buckhead community of Atlanta, Georgia on a two-acre site. With it&#39;s spiraling architectural style, this high-profile project creates a unique landmark in Buckhead.</p>
<p>
	The building design incorporates a new twist on the growing popularity of mixed-use design by going vertical, rather than horizontal, with the 50-story structure.&nbsp; The building exterior of all glass curtainwall was designed as a piece of art or sculpture to fit in with the site and skyline of the area.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 17:10 GMT</pubDate>
  </item>
  
  <item>
    <title>Cobb Energy Performing Arts Centre</title>
    <link>http://www.dpr.com/projects/cobb-energy-performing-arts-centre</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/cobb-energy-performing-arts-centre#when:17:00</guid>
    
    <content:encoded><![CDATA[<p>
	The Cobb Energy Performing Arts Centre is a 2,754-seat world-class theater with a 26,500-sq.-ft. banquet hall with a full-service kitchen, a 600-seat ballroom, production spaces, administrative offices and building services facilities.&nbsp; A four-level, 700-space parking deck was also constructed adjacent to the theatre to provide easy access to the facility. The theatre is designed to accommodate a broad range of potential uses including Broadway touring shows, touring popular music concerts, dramatic events, comedy acts, ballet, opera and corporate events.</p>
<p>
	The theatre is built in the style of traditional European theaters, yet features state-of-the-art comfort and technology. Sound acoustical joints keep all vibrations from the structure so no noise will disturb the shows.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Sun, 25 Mar 2012 17:00 GMT</pubDate>
  </item>
  
  <item>
    <title>Clif Bar Headquarters</title>
    <link>http://www.dpr.com/projects/clif-bar-headquarters</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/clif-bar-headquarters#when:23:32</guid>
    
    <content:encoded><![CDATA[<p>
	The Clif Bar Headquarters transforms a World War II valve manufacturing facility into a workplace haven for the outdoor enthusiasts at Clif Bar. As an adaptive reuse LEED-Platinum project, it features an open office working environment; onsite childcare; a theater space; a caf&eacute; and an employee wellness area with a yoga room, dance studio, weight room, bouldering wall, shower/locker facilities and access to five onsite fitness trainers, two massage rooms and a hair salon.<br />
	<br />
	This is one of the first buildings to comply with California&#39;s new energy efficiency standards, the toughest in the nation. It includes the first &ldquo;smart&rdquo; solar array in North America over 500 kWh, providing 100% of the office electricity. Clif provides all employees with 30 minutes of paid time to exercise each day and its Cool Commute program has also helped 42 employees purchase hybrid or biodiesel cars, raising their fuel efficiency.<br />
	<br />
	The 2-story open office is flooded with natural light and four interior gardens deliver bright sunlight, fresh air and rain to the plants and greenery inside. These courtyards and a series of living walls subdivided work areas, while at the same time providing beauty, inspiration and a physical connection to the outdoors.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 04 Jan 2012 23:32 GMT</pubDate>
  </item>
  
  <item>
    <title>Florida International University Academic Health Center 4</title>
    <link>http://www.dpr.com/projects/florida-international-university</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/florida-international-university#when:23:31</guid>
    
    <content:encoded><![CDATA[<p>
	This 137,000-sq.-ft. Lab/Classroom Complex will provide the University with advanced research labs, a 10,000 sq. ft. transgenic space, BSL2 labs, flexible research space, study rooms for graduate students, offices, and faculty/student gathering spaces that will promote collaborative work.</p>
<p>
	The project is a 6-story, cast-in-place concrete frame with PSI joist system; exterior skin consisting of architectural precast, curtainwall, punched openings, metal panels; and stucco/paint or other architectural finish system. The interior consists of classrooms, common areas and built-out wet and dry lab space. Other trades including miscellaneous metals, architectural woodwork and cabinetry, caulking and waterproofing, roofing, doors/frames/hardware, overhead doors, interior glazing assemblies and storefront, drywall assemblies and insulation, tile, carpet, resilient and sheet vinyl flooring, epoxy coatings, terrazzo flooring, acoustical ceilings, paint, acoustical wall panels, Division 10 Specialties, laboratory equipment and casework, elevators, and MEP/FP systems.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 04 Jan 2012 23:31 GMT</pubDate>
  </item>
  
  <item>
    <title>Rapides Regional Medical Center Expansion and Renovation</title>
    <link>http://www.dpr.com/projects/rapides-regional-medical-center-expansion-and-renovation</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/rapides-regional-medical-center-expansion-and-renovation#when:16:17</guid>
    
    <content:encoded><![CDATA[<p>
	This project included a new four-story, 125,000-sq.-ft. medical tower with 25-bed emergency department, 26-bed intensive care unit and two floors with 72 medical/surgical beds. The project also included a 4,500-sq.-ft. renovation to the main hospital lobby.</p>
<p>
	The project also included shell spaces for a future Library and future Dialysis unit.&nbsp; Through intricate coordination, DPR was able to incorporate the finish out of both future units during the construction of the main project. General conditions were shared between projects, saving the facility considerable expense. These savings contributed to making the build-outs affordable to complete during the main project.</p>
<p>
	The project had several challenges, both expected and unexpected. Availability of manpower was an issue due to the after-effects of hurricane Katrina. DPR&rsquo;s strong relationships with national subcontracting firms helped the team staff the project. The national firms supplemented the local forces that were available, and were instrumental to the success of the project.</p>
<p>
	What was unexpected was that Louisiana had the wettest, coldest winter in seven years.&nbsp; This resulted in more than 142 rain days during construction of the tower.&nbsp; The owner allowed a 20-day schedule extension; the remaining 122 days were made up through overlapping trade schedules, and off-hours and weekend work.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Thu, 01 Dec 2011 16:17 GMT</pubDate>
  </item>
  
  <item>
    <title>Alkek IBT Institute Fourth Floor Buildout</title>
    <link>http://www.dpr.com/projects/alkek-ibt-institute-fourth-floor-buildout</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/alkek-ibt-institute-fourth-floor-buildout#when:15:17</guid>
    
    <content:encoded><![CDATA[<p>
	This project involved and 18,000-sq.-ft. finishout of laboratories on the fourth floor of an 11-story building. One project challenge was the change-out an air-handling unit serving animal rooms that could not be shut down. DPR had the unit shipped in pieces then reassembled it onsite, completing the work within just one week. DPR proposed completing the project 35 days faster than the University required, and completed on time despite owner-initiated changes.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Thu, 01 Dec 2011 15:17 GMT</pubDate>
  </item>
  
  <item>
    <title>University of Texas MD Anderson Cancer Center BMT / GMP Lab Renovation</title>
    <link>http://www.dpr.com/projects/bmt-gmp-lab-renovation</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/bmt-gmp-lab-renovation#when:03:13</guid>
    
    <content:encoded><![CDATA[<p>
	Combining expertise in a range of disciplines, including Food and Drug Administration (FDA)-validated biotech projects, semiconductor and interior healthcare renovations, DPR completed the renovation of the largest Blood and Marrow Transplantation/Good Manufacturing Practices (BMT/GMP) laboratory in the country for M. D. Anderson Cancer Center&rsquo;s Houston campus. The 16,000-sq.-ft. lab,&nbsp; is situated alongside critical patient care areas on the 14th floor of Lutheran Tower and includes an ISO Level 7 cleanroom (less than 83,200 microsized dust particles per cubic meter) and was built in line with FDA-validation procedures.</p>
<p>
	The project, situated alongside critical patient care areas on the 14th floor of Lutheran Tower, required a disciplined approach to infection control. Constant communication with the facility&rsquo;s staff, doctors and nurses was a necessity. DPR coordinated all activity with staff, working around the day-to-day needs of the patients, with their safety and comfort a driving focus.</p>
<p>
	Critically ill patients occupied adjacent floors. As part of a rigorous infection control plan, DPR sealed draft stops and ductwork to ensure debris from the construction area did not enter patient rooms. Negative pressure machines, tacky mats, HEPA filters and other barriers were used as well.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Thu, 01 Dec 2011 03:13 GMT</pubDate>
  </item>
  
  <item>
    <title>Round Rock Medical Center Expansion and Renovation</title>
    <link>http://www.dpr.com/projects/round-rock-medical-center-expansion-and-renovation</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/round-rock-medical-center-expansion-and-renovation#when:02:49</guid>
    
    <content:encoded><![CDATA[<p>
	The project involved the construction of a new three-level, 130,000-sq.-ft. patient tower tied in to the existing hospital, as well as renovations and new two-story central plant. The new patient tower includes a surgery center, 18-patient post-acute-care and recovery suites, 12-bed intensive care unit and 34 private patient beds. Each phase of the project was turned over to the owner early, and three phases were completed with Zero Defects, or no outstanding punchlist items at substantial completion.</p>
<p>
	The footprint of the new patient tower was directly over the location of the original utilities&#39; path to the hospital. Rather than shut the water off to the hospital while tying into the new line, the team used this new approach: temporary &ldquo;saddles&rdquo; were attached to the exterior of the 8-inch water main in two sections, and then connected to a nitrogen source. The water in the pipes in the work area froze, allowing workers to cut open the pipe and install the new line. Work had to be performed quickly, before the frozen water could melt, potentially sending hundreds of gallons of water through the open pipe.</p>
<p>
	To drill 20-foot piers inside the occupied pharmacy, DPR built temporary walls to encapsulate work activity within the partitions. A Bobcat was brought in to drill the piers and worked within the temporary walls. Exhaust from the Bobcat was released from the building via a 50-foot flexible steel tube attached to the muffler. The tube extended out of the work area, down the hall and out of a side door of the hospital.</p>
<p>
	To install the structural steel into the piers, a hole was cut in the roof for cranes to "fly" the steel in. To protect staff, DPR timed the incoming piers with the staff; each time a new piece came in, the staff would leave the area for 20 minutes (it is against OSHA regulation to allow major lifts over occupied spaces) then return when the coast was clear.</p>
<p>
	The project required the relocation of the employee parking lot. The owner&#39;s original schedule called for a new lot to be built prior to beginning construction of the new building. DPR recommended several approaches to &ldquo;parking control&rdquo; to allow work to begin on both phases at once. DPR built sidewalks, covered walkways, brought in a shuttle van and built a bus stop pavilion to make the employee&#39;s trek from an outer lot easier. By starting the new lot and building at the same time, six months were shaved from the schedule.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Thu, 01 Dec 2011 02:49 GMT</pubDate>
  </item>
  
  <item>
    <title>Round Rock Medical Center C-Section Suite, Cath Lab and Med/Surg</title>
    <link>http://www.dpr.com/projects/round-rock-medical-center-c-section-suite-cath-lab-and-med-surg</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/round-rock-medical-center-c-section-suite-cath-lab-and-med-surg#when:02:46</guid>
    
    <content:encoded><![CDATA[<p>
	This complex, phased project&mdash;winner of Texas Construction Magazine&#39;s Best of 2004-Best Healthcare Project&mdash;took place entirely in and around sensitive hospital operations. There were four main components to the project:</p>
<ul>
	<li>
		450-sq.-ft. C-Section addition</li>
	<li>
		4,000-sq.-ft. Cardiac Catheterization addition</li>
	<li>
		20 Med/Surg Patient rooms, 9,600-sq.-ft., buildout of shell space</li>
	<li>
		Relocation of existing utilities</li>
</ul>
<p>
	The C-Section suite was tied into the building in an alcove space of the central courtyard of the hospital. Because of this &ldquo;locked-in&rdquo; location, cranes were used to excavate, dump in select fill and place structural steel &ndash; from the staging area in the parking lot, over the building, to the inside of the courtyard. To comply with OSHA and DPR safety requirements (which do not allow any load to be lifted over people), the team coordinated with the hospital to lift in and out when there were no scheduled C-Sections (the area under the lift path is the birthing center). DPR used spotters inside the hospital along the lift path to keep people from walking through during a lift, and to alert the team when an emergency C-Section needed to come through. In those instances, work was halted immediately and resumed only when the team could be sure there was no traffic.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Thu, 01 Dec 2011 02:46 GMT</pubDate>
  </item>
  
  <item>
    <title>North Austin Medical Center Expansion and Renovation</title>
    <link>http://www.dpr.com/projects/north-austin-medical-center-expansion-and-renovation</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/north-austin-medical-center-expansion-and-renovation#when:02:45</guid>
    
    <content:encoded><![CDATA[<p>
	New 175,000-sq.-ft., three-level patient tower, with 23,000-sq.-ft. renovations to existing hospital. Project includes vertical and horizontal expansion to women&#39;s center, with surgery center and medical offices on the ground floor.</p>
<p>
	One of the most critical challenges was removing exterior precast panels to expose the building substructure. Field measurements for steel tie-in points, exact dimensions of concrete edges, and structural openings all had to be verified. However, removing the panels left the building&#39;s exterior skin exposed to weather and environmental breaches to Infectious Disease Controls. This condition was more exaggerated in some cases because some of the panels were three stories tall, opening three floors at a time to the exposures referenced.</p>
<p>
	The DPR staff engaged in many creative methods to get this segment of work done and still keep the areas behind the precast in operation. It was necessary to constantly come up with new ways to install temporary weather protection and monitor the installations. Coordination with the facility and end user for shut downs of the space was continuous. The work was completed with no incidents to patients, staff, or the facility.</p>
<p>
	The team created an electronic model of the concrete structure using Building Information Modeling (BIM) tools. Because the details could be accurately modeled electronically, potential clashes were resolved before workers broke ground. DPR was also able to give the subcontractor a 3D view of what the underground work looked like, resulting in a higher level of quality.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Thu, 01 Dec 2011 02:45 GMT</pubDate>
  </item>
  
  <item>
    <title>Capital Imaging Center</title>
    <link>http://www.dpr.com/projects/capital-imaging-center</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/capital-imaging-center#when:02:39</guid>
    
    <content:encoded><![CDATA[<p>
	DPR constructed this sophisticated, medical office build-to-suit project on time and on budget despite winter rains that substantially delayed the project. The 105,000-sq.-ft. imaging facility included structural and other requirements associated with working with magnetic resonance imaging (MRI) equipment---the main facility is located in the basement, with half of the first floor dedicated to breast-imaging. The balance of the first floor, as well as the second floor are dedixcated to a 170-stall parking structure.</p>
<p>
	Urban development on a zero lot line is not without its challenges. With the lack of a material storage area, DPR developed a "just in time" material delivery system. Materials were delivered and installed on the day needed and not a moment before. In addiiton, the project team developed a site specific safety plan that ensured the safety and minimal disruption to the residents of an apartment complex that was in close proximtiy of the site.&nbsp;</p>
<p>
	&nbsp;</p>
<p>
	&nbsp;</p>
<p>
	&nbsp;</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Thu, 01 Dec 2011 02:39 GMT</pubDate>
  </item>
  
  <item>
    <title>The Heart &amp; Vascular Hospital at Clear Lake Regional Medical Center</title>
    <link>http://www.dpr.com/projects/the-heart-vascular-hospital-at-clear-lake-regional-medical-center</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/the-heart-vascular-hospital-at-clear-lake-regional-medical-center#when:01:28</guid>
    
    <content:encoded><![CDATA[<p>
	When this 207,000-sq.-ft. heart hospital broke ground, the plans called for a four-story,160,000-sq.-ft. building. Several months in to construction, the hospital decided to add an additional two floors. Despite this major addition, the facility was completed just two weeks following the original completion date. The facility includes a six-story tower, pedestrian bridge to the existing hospital, 84 beds and operating rooms, intensive care beds, a coronary care unit, catheterization laboratories and private inpatient beds.</p>
<p>
	The soil in Clear Lake is sandy, requiring massive footings. Rather than dig individual footings, DPR excavated the entire area, poured footings and plinths, then backfilled around them. Excavating a single large area meant there was no risk of the cave-ins associated with digging footings in sandy soil, and two weeks were shaved from the schedule.</p>
<p>
	With three of four floors in place, the owner added two floors to the scope of the project. Designs were not complete, and rebar&mdash;which had a lead time of six weeks&mdash;is typically not ordered until drawings are farther along. Rather than push the schedule out, DPR pre-ordered the rebar, estimating quantities based on the previous floors and allowing for changes in the field to accommodate the larger ductwork required for floors five and six. The anticipated field changes were made quickly, ultimately saving time on the scheduled compared to ordering rebar when designs were complete.</p>
<p>
	The addition of two floors of cast-in-place concrete would have exceeded the soil bearing capacity of the site, so the design of the roof was changed to steel, which is long lead. To keep the project moving forward, a temporary rubber roof was installed so finishouts could begin on the first four floors. Waterproof sheetrock was used on top-out walls in some areas where wall framing and ductwork installation could begin. The cost of the temporary roof&mdash;approximately $70,000&mdash;paid for itself in time saved four times over. It also allowed the team to essentially stay on the same schedule proposed before the addition of two floors. Installation of a connector bridge from the heart hospital to the main hospital also presented challenges. Created using more than 100 tons of steel, the 400-ft. bridge was installed over a busy county road. The team was required to coordinate with several entities to close the road while sections of the bridge were installed.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Thu, 01 Dec 2011 01:28 GMT</pubDate>
  </item>
  
  <item>
    <title>One Kearny/710 Market</title>
    <link>http://www.dpr.com/projects/1-kearny-710-market</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/1-kearny-710-market#when:21:56</guid>
    
    <content:encoded><![CDATA[<p>
	Logistically challenging, the &ldquo;One Kearny&rdquo; project, located at the heart of downtown San Francisco, is short on lay down area but long on opportunities to prove technical expertise. Situated at the corner of Market and Kearny streets in San Francisco&#39;s Financial District, One Kearny is a Class A redevelopment combining three buildings that represent three distinct architectural periods dating back to 1900.</p>
<p>
	DPR&#39;s project manager for the $30 million, 60,000-sq.-ft. new addition to the project. &ldquo;One Kearny includes the demolition of an existing three-story building, ground-up seismic construction of an 11-story high rise on one of the most logistically challenging sites in the city, the historical and seismic renovation of an existing 12-story building constructed in 1902, and the modernization of a building designed by famous architect Charles W. Moore.&rdquo; said Jim Lacy, When completed in January 2009, the three adjoining buildings&mdash;the new 60,000-sq.-ft. building, the historic 1902 64,000-sq.-ft. building and the Charles W. Moore &ldquo;annex,&rdquo; which was added to the 1902 Building in 1956&mdash;will become one, with a shared opening between the three different addresses, and offer boutique office space and retail space on the ground floor.</p>
<p>
	Demolition of the existing three-story building began in August 2007 and construction started on the new 11-story addition in November 2007. With zero lay down area and only 800 sq. ft. of parking lane to deliver materials, the project team has had to employ a tower crane, set 240 ft. above one of San Francisco&#39;s busiest intersections, to immediately pick up materials and place them into the building.</p>
<p>
	Along with the tight Market Street location, the construction team is challenged with maintaining the integrity of the two historic buildings, while constructing the attached contemporary steel-framed addition designed by San Francisco architect and structural engineer Charles Bloszies. The project also includes a complete state-of-the-art seismic renovation, ADA compliant upgrades throughout the development, and installation of the latest telecommunications and security systems. In addition, new elevators and a new, energy-efficient curtain wall, which must look exactly the same as the old curtain wall to maintain the structure&#39;s historical building status, will be installed for the annex project. &ldquo;We&#39;re delighted to be able to prove the depth of our technical expertise on this project,&rdquo; said Lacy, &ldquo;and it&#39;s equally as exciting to preserve and protect a significant piece of San Francisco&#39;s history.&rdquo;</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 30 Nov 2011 21:56 GMT</pubDate>
  </item>
  
  <item>
    <title>Alexza Pilot Plant and Laboratory/Office Remodel</title>
    <link>http://www.dpr.com/projects/pilot-plant-and-lab-office-remodel</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/pilot-plant-and-lab-office-remodel#when:01:44</guid>
    
    <content:encoded><![CDATA[<p>
	The Alexza Pilot Plant and Lab/Office Remodel project consisted of demolition of existing office space and construction of a 10,000-sq.-ft. Phase III pilot plant and a 45,000-sq.-ft. lab and office renovation. It also included a new utility yard.</p>
<p>
	The pilot plant, completed in May 2007, contains areas for gowning and lockers, cleaning preparation, Class 10,000 sampling/dispensing and labeling, Class 10,000 drug solution, coating, assembly and packaging, waste storage, bathrooms and showers, server room and shipping/receiving and warehouse. It also included an environmentally controlled crystalization room. DPR assisted in the installation of the owner-supplied pouching machine, which arrived in eight pieces and had to be carefully moved into the space and assembled over three days.</p>
<p>
	Challenges on this project included the design/build MEP systems and the aggressive design schedule. In order to meet deadlines, it was imperative that materials were ordered and released on time. The design approval process with the city, while challenging to the schedule, proved to be a great opportunity to develop a good working relationship with the city inspector.</p>
<p>
	To ensure that the end users would have a space that met their daily needs, Alexza production and science managers were accompanied on frequent jobwalks with clipboards and forms and asked to identify issues they had with the space.</p>
<p>
	The lab and office renovation consists of new open office space, structural upgrades to support additional mechanical equipment and chemical labs. The scope of work for the labs includes casework, fume hoods, nitrogen, clean air and hydrogen.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 30 Nov 2011 01:44 GMT</pubDate>
  </item>
  
  <item>
    <title>Abbott Vascular Building C Campus Expansion</title>
    <link>http://www.dpr.com/projects/building-c-campus-expansion</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/building-c-campus-expansion#when:01:34</guid>
    
    <content:encoded><![CDATA[<p>
	DPR helped Abbott Vascular increase its ability to manufacture a new stent at their Santa Clara facility with the completion of a renovation project that included new cGMP manufacturing space in a large, ballroom-type configuration with several multi-use, multi-functional utility locations. The remodel also included support labs and offices, seismic upgrades and a new central plant.</p>
<p>
	As a validated facility, this project required a significant amount of documentation. Highly experienced in building validated facilities, the DPR team began preparing for the validation process before a single tool was picked up. By developing the documentation plan early, DPR eased the process of compiling and delivering the 40+ binder turnover package.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 30 Nov 2011 01:34 GMT</pubDate>
  </item>
  
  <item>
    <title>FormFactor Wafer Probe Card Manufacturing Facility</title>
    <link>http://www.dpr.com/projects/wafer-probe-card-manufacturing-facility</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/wafer-probe-card-manufacturing-facility#when:01:08</guid>
    
    <content:encoded><![CDATA[<p>
	A fluid schedule and sticking to DPR&#39;s fundamental business practices&mdash;such as a rolling completion list and weekly job walks with the owner&mdash;led to the successful transformation of a cold shell warehouse into a one-of-a-kind wafer probe-card-manufacturing facility in 10 short months for FormFactor, Inc. As a leader in the design, development, manufacture, sale and support of high-performance advanced semiconductor wafer probe cards, FormFactor looked to DPR to handle the first renovation on the company&#39;s new Livermore, CA campus that featured 24,000 sq. ft. of manufacturing space, including Class 100 and Class 1,000 production suites, as well as 14,000 sq. ft. of tenant improvements.</p>
<p>
	As part of the renovation, the team performed structural upgrades to the building&#39;s roof to support six new make-up air units and removed half of the building&#39;s slab and depressed it two feet to accommodate the cleanroom access flooring. The team also installed 112 High-Efficiency Particulate Air (HEPA) plenums and 60 recirculation units. Alongside the building, DPR built a back service pad for the central utility plan, which includes chilled water, condenser water, a boiler and an emergency generator.</p>
<p>
	Despite the highly complex nature of the project, DPR delivered Phase 1 a day ahead of schedule with zero defects, and the project was turned over to the owner with no outstanding change orders.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Wed, 30 Nov 2011 01:08 GMT</pubDate>
  </item>
  
  <item>
    <title>City of Austin New System Control Center</title>
    <link>http://www.dpr.com/projects/new-system-control-center</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/new-system-control-center#when:23:51</guid>
    
    <content:encoded><![CDATA[<p>
	Conversion of 120,000-sq.-ft. former semiconductor testing facility to data center, energy control center, and offices. The scope of the project includes salvage and re-use of equipment and materials, renovations, new construction, and site work. Project is pursuing LEED Silver certification.</p>
<p>
	Building Information Modeling (BIM) tools are being used to streamline coordination of equipment installation and to resolve clashes before designs are complete. At the construction mid-way point, the team has identified 400 major clashes that have led to re-sizing of ductwork, lowering ceilings and re-routing of mechanical and electrical systems. The mechanical team estimates that the electronic coordination has saved them approximately two months on the schedule and $50,000-$10,000 due to lack of conflicts.</p>
<p>
	DPR created the architectural, structural and miscellaneous support models. The mechanical and electrical subcontractors each created their scopes in the model, as did the telecommunication and fire protection contractors. The subcontractors have gained the most use of the models through multidiscipline coordination, shop drawing creation and visuals to attach to RFIs.</p>
<p>
	At the end of the project, the model will be handed over to the owner to use with their &lsquo;as-built&rsquo; documentation and facility management.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Tue, 29 Nov 2011 23:51 GMT</pubDate>
  </item>
  
  <item>
    <title>CHRISTUS New Data Center</title>
    <link>http://www.dpr.com/projects/christus-new-data-center</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/christus-new-data-center#when:23:49</guid>
    
    <content:encoded><![CDATA[<p>
	New Tier 3, 47,000-sq.-ft. data center which includes 15,000-sq.-ft. data center white space, 20,000-sq.-ft. office and 12,000-sq.-ft. electrical support space. The facility includes a Security Operations Center (SOC) and a Network Operations Center (NOC).</p>
<p>
	The owner&#39;s initial plan called for two distinct phases: shell construction and data center finishout, with demobilization from the site between the two. This was to accommodate the company&#39;s fiscal year and funding availability. DPR recommended compressing the shell construction by two months and starting later, eliminating the need for additional demobilization/mobilization and saving on the overall budget.</p>
<p>
	The electrical underground design would not be ready in time to meet the new accelerated schedule. Completion of the building slab was a critical schedule milestone, as it was to serve as the casting bed for the tilt-up panels. However, the electrical underground design would not be ready in time for the new accelerated schedule. Under the original schedule, the massive amount of electrical conduit needed would have been installed below the slab prior to it being poured. To allow construction to proceed while electrical design was in progress, the project&#39;s structural engineers analyzed the foundation grade beam structure and made recommendations for proceeding with the slab. The approach was to utilize the four feet of flowable, lightweight concrete under the exterior grade beams for access. When the building construction was complete, a portion of the interior slab was removed and sections of the lightweight concrete excavated. Electricians were then able to run conduit from the interior of the building to the exterior yard while the interior build-out progressed.</p>
<p>
	The city utility also did not have sufficient infrastructure to support the facility by the accelerated completion date. They agreed to have power ready in time for the original completion date but could not guarantee service for the compressed construction schedule. The team enlisted a temporary services design and implementation company to design and provide temporary cooling and dehumidification of the interior to allow sensitive activities to continue without hindering the schedule.</p>
<p>
	<a href="http://www.christushealthhosting.com/">http://www.christushealthhosting.com/</a></p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Tue, 29 Nov 2011 23:49 GMT</pubDate>
  </item>
  
  <item>
    <title>Advanced Micro Devices Research and Development Relocation</title>
    <link>http://www.dpr.com/projects/research-and-development-relocation</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/research-and-development-relocation#when:23:45</guid>
    
    <content:encoded><![CDATA[<p>
	Finishout of 60,000 sq. ft. of research and development lab space on AMD&#39;s Lone Star campus. AMD&#39;s fast schedule was driven by their need to consolidate their operations to increase company efficiency. All construction took place in an occupied testing facility and there was no unscheduled downtime.</p>
<p>
	The R&amp;D consolidation project brought many separate work groups together into a single open work area. Each of these groups has different equipment with different MEP requirements, different schedules, and different overall project needs.&nbsp;To help each user group visualize the layout of the new space and get their feedback on changes prior to installing work, DPR walked each through a mock-up of the space. Before laying out floors and installing equipment as it was shown on the plans, DPR ran everything through the end-users first. Each was shown &ndash; through mockups, sketches, blueprints &ndash; what their space would &lsquo;look&#39; like to help them visualize what they needed. Most of the silicon chip scientists moving in to the facility had never built a lab before and found this exercise helpful to pinpoint exactly what they would need.</p>
<p>
	The fast schedule left no time for shop drawing approvals or prefabrication.&nbsp;On mechanical and electrical-heavy projects like this, time is typically spent early on to review submittals with subcontractor teams, receive their approvals, and prefabricate much of the work. Because of the fast pace of this project, there was no time to review shop drawings or prefabricate MEP systems. Everything had to be approved, built, and installed on site and on the fly.</p>
<p>
	DPR supervised and coordinated the work on site as it was installed. Field engineers from the mechanical and electrical teams worked on site with DPR to hand sketch single sections of work. The sketches were emailed to engineers for approval, then fabricated and installed. DPR&#39;s superintendent coordinated the work of the teams to ensure the work &ndash; performed under raised floor and in the same space &ndash; continued efficiently without workers getting in each other&#39;s way.</p>
<p>
	Part of DPR&#39;s scope of work was to oversee the decommissioning, moving, and reinstallation of more than 150 different kinds of microchip research and testing tools. Each tool move involved the tool operator, riggers, movers, mechanical subs, electrical subs, and DPR. Each tool also had different requirements for downtime, MEP systems, and start-up, and a constantly changing schedule for when it could be moved, based on current production schedules.</p>
<p>
	DPR took a hands-on, tool-by-tool approach to supervising the tool moves. A mechanical/electrical coordinator was stationed at each end of the move to monitor the shutdown and startup. The superintendent at the project site coordinated installation subcontractors, making sure each parties was there when needed and that work was performed in the right order. For example, electrical connections must be made before compressed air, followed by process water. This process was repeated as tools were ready to be moved over the course of four months.</p>
<p>
	After project was finished, DPR had to take it all offline to install 120 zone valves in less than 48 hours at the request of the owner. These new process cold water zone valves were added to allow the owner to isolate smaller sections of the system for maintenance work, so all tools don&#39;t have to be shut down for one repair.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Tue, 29 Nov 2011 23:45 GMT</pubDate>
  </item>
  
  <item>
    <title>AMC Theaters at Vallco Fashion Park</title>
    <link>http://www.dpr.com/projects/amc-theaters-at-vallco-fashion-park</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/amc-theaters-at-vallco-fashion-park#when:22:33</guid>
    
    <content:encoded><![CDATA[<p>
	DPR Construction built the 16-theater movie megaplex with seating capacity for 3,500 people above an existing occupied shopping center, including mall upgrades, a 120,000-sq.-ft. addition and a new center atrium and lobby renovation. Due to the theater&rsquo;s location, the logistical challenges were many, not the least of which was working in the middle of an occupied shopping mall. The project required extending over 100 structural columns four feet vertically into the existing roof. The column footings on the main and second floors had to be expanded and reinforced to support the new platform, requiring digging into walls to expose the columns which often had to be done in spaces occupied by mall tenants.</p>
<p>
	The project completed in March of 2007.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Tue, 29 Nov 2011 22:33 GMT</pubDate>
  </item>
  
  <item>
    <title>San Francisco Asian Art Museum</title>
    <link>http://www.dpr.com/projects/asian-art-museum</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/asian-art-museum#when:21:05</guid>
    
    <content:encoded><![CDATA[<p>
	Converting the magnificent San Francisco Main Library in the heart of San Francisco&rsquo;s Civic Center into the San Francisco Asian Art Museum proved to be an amazing historic renovation feat. The three-story downtown building, built in 1917, was condemned in 1989 after suffering damage in the Loma Prieta Earthquake.</p>
<p>
	The renovated building is composed of a concrete frame on 210 base isolators designed to allow the new landmark to withstand an 8.3 magnitude earthquake. A moat around the perimeter accommodates sway during a seismic event.</p>
<p>
	DPR teamed up with LEM Construction Inc. in a joint venture to serve as the general contractor for the restoration of the exterior granite skin fa&ccedil;ade and interior renovation of the great hall, grand staircase, and loggia, as well as the addition of a new floor and a 50-ft. tall skylight&mdash;a signature of designer Gae Aulenti that now floods the once dark library with natural daylight.</p>
<p>
	The high-profile rehabilitation and adaptive re-use project consumed 26,000 cubic yards of concrete, 6,000 tons of steel, 30,000 sq. ft. of glass, 50 miles of electrical wiring, and 11,000 sq. ft. of Italian Basaltina stone flooring (the same that is used in the Vatican).</p>
<p>
	The old Main Library offers 121,500 usable sq. ft. of which approximately 37,000 sq. ft. is allocated to galleries, a 30 percent increase over the gallery space the Asian Art Museum had at its previous location in Golden Gate Park.</p>
<p>
	The amount of structural renovation required to stabilize and seismically strengthen the building was challenging. The structural work alone took two-and-a-half years to complete and involved the installation of 14 shear walls up to three ft. thick that ran from the ceiling to the basement. Due to limited site access in the highly dense Civic Center area, most of the steel had to be hand-rigged (rather than using a crane). Approximately 1,300 laborers, carpenters, ironworkers, glaziers, plasterers, masons, plumbers, fitters, electricians, and other professionals worked together to safely complete more than a million hours of construction over nearly four years.</p>
]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Tue, 29 Nov 2011 21:05 GMT</pubDate>
  </item>
  
  <item>
    <title>Kforce.com Corporate Headquarters</title>
    <link>http://www.dpr.com/projects/kforce.com-corporate-headquarters</link>
    <guid isPermaLink="false">http://www.dpr.com/projects/kforce.com-corporate-headquarters#when:18:27</guid>
    
    <content:encoded><![CDATA[<p>
	Hardin Construction Company, LLC completed construction of Kforce.com&#39;s World Headquarters in an amazing 11-month schedule.</p>
<p>
	Hardin was challenged by Highwood&#39;s Properties and Kforce to provide them with a Class &ldquo;A&rdquo; office building utilizing a fast-track schedule which could accommodate the relocation of five of their branch offices into one facility.&nbsp; As this building was the first of its kind in the historic Ybor City area. Careful consideration was given to the aesthetics of the building.&nbsp; Various brick and building colors were utilized in order to match Centro Asturiano - a 100-year-old social club, which is a focal point of local gatherings and community events.</p>
<p>
	Kforce.com&#39;s new facility was designed to provide a casual environment which could meet every need of the Kforce.com employee by enhancing the workplace environment.&nbsp; Of the 138,000-sq.-ft. facility, 5,000 sq. ft. is dedicated to an indoor, full-service cafeteria with dining facilities and full catering services.&nbsp; An additional 15,000 sq. ft. is comprised of a full exercise arena containing state-of-the-art exercise equipment, locker rooms and showers, and a full, NCAA regulation basketball court.</p>
<p>
	The office building itself is built utilizing a steel frame structure with precast concrete and glass skin.&nbsp; Kforce chose to install an aluminum &ldquo;eyebrow&rdquo; around the entire perimeter of the building creating consistent shade to the building exterior in order to maximize the energy efficiency, yet providing an eye pleasing aesthetic appeal.&nbsp; The finished exterior product allowed construction to meet the owners schedule and budget needs while providing the building with a much richer look and feel.</p>
<p>
	The interior of the building continues to incorporate the historical look of the area by utilizing quarter-sawn cherry panel finishes and furniture.&nbsp; The lobby floor is comprised of terrazzo, and is accented on the second and third floors with Mandarin style art.&nbsp;</p>
<p>
	Safety was a concern throughout the project due to the dangers associated with erecting and securing the steel and precast walls immediately adjacent to high voltage (69kv) backup power lines which service the downtown Tampa area.&nbsp; Through careful implementation of Hardin&rsquo;s safety plan, including daily safety meetings and subcontractor awareness, the project was completed successfully with no lost-time accidents.</p>
<p>
	This facility was instrumental in the revitalization for the west side of Ybor City, and is a unique example of how new construction and state-of-the-art facilities can be incorporated into an historical environment with ease.</p>]]></content:encoded>
    <dc:subject></dc:subject>
    <pubDate>Mon, 19 Apr 2010 18:27 GMT</pubDate>
  </item>
  

    
    </channel>
</rss>