This was DPR’s first project within Mercy Hospital. It consisted of a complete renovation of Mercy Hospital’s IV and Chemo Preparation area. During the duration of the project, the hospital’s operations within this 1,180-sq.-ft. room were relocated to a temporary space adjacent to the construction area. 

The location of the project site was challenging for construction traffic and hospital operations, so the team identified a secondary means of travel. The team implemented a plan that allowed access to the project site through an approved back-of-house path.

DPR self-performed the acoustical ceilings, drywall and doors. This AHCA-inspected (Agency for Healthcare Administration) project included a new exterior exhaust fan, ductwork, lighting fixtures, interior finishes, and stainless steel furniture.